Santa Barbara Boulevard - Widening Project

Phase III of this project is on going.
Provide your comments, and get on our mailing list.

Project Limits
Gleason Parkway to Pine Island Road

Project Start Date
November 2006

Project Description
The first major corridor project to begin construction as part of Cape Coral’s Five-Year Roadway Improvement Project is Santa Barbara Boulevard, which is being widened to six lanes from Gleason Parkway to Pine Island Road. The project will be built in three phases.

  1. Phase I – Widen the Cadman Canal Bridge (near SunSplash) (Completed)

  2. Phase II-  Widen Santa Barbara Boulevard between SE 8th Street and Pine Island Road, including the Hancock Bridge Parkway Extension (west of Santa Barbara Boulevard) (Completed)

  3. Phase III—Widen Santa Barbara Boulevard between Gleason Parkway and SE 8th Street, and north of Hancock Bridge Parkway through the SR 78 intersection.

The road construction activities include survey work, utility relocation and drainage improvements. Phase III, from Gleason Parkway to SE 8th Street and Hancock Bridge Parkway to 1500 feet north of SR 78/Pine Island Road (Summer 2008).