Del Prado Boulevard - Widening Project


This project is complete

Click here for high-resolution map

 

Project Limits
Pine Island Road to Kismet Parkway

Project Description
Del Prado Boulevard road construction involved the widening of the existing roadway from four to six lanes beginning just south of Pine Island Road to just north of Kismet Parkway. The project was scheduled to be built in five phases and take approximately three years in its entirety.

These are:

  1. Phase I: Off-site bridges--NE 14th Place and NE 17th Place (crossing Jaguar Canal) - Complete
  2. Phase II: Mainline Bridge---Del Prado Boulevard over Jaguar Canal - Complete
  3. Phase III: Off-site Bridge—NE 16th Place over Zurich Canal - Complete
  4. Phase IV: Mainline Bridge—Del Prado Boulevard over Zurich Canal - Complete
  5. Phase V: Roadway—Del Prado Boulevard to Kismet Parkway - Ongoing

In addition to widening Del Prado Boulevard, the project included widening of two existing bridges and the construction of three new bridges. Improvements to the roadway widening include expanded right-of-way, landscaping, paved multi-use paths, street lighting, curbing and new traffic signals.

Return to Projects

Segment Map Update

View Segment Map

Project Fact Sheet

View Fact Sheet

Project Aerials


July 2011

June 2011

May 2011

Del Prado November 2009 Del Prado November 2009 Del Prado November 2009 Del Prado November 2009 Del Prado November 2009 Del Prado November 2009 Del Prado November 2009 Del Prado November 2009